Datum FRN2 is a data centre project in Cody Technology Park, Farnborough GU14 0LX. The reported operator is Datum.

United Kingdom

View Datum FRN2 on the map

Construction

Evidence reviewed 10 Nov 2026

About this location

Datum FRN2 is a data centre project in Cody Technology Park, Farnborough GU14 0LX. The reported operator is Datum.

Status evidence

Current operator explicitly states FRN2 construction began December2025 and remains the fourth DC under construction. Existing FRN1 is operating; completion is not inferred from a forecast. Exact publication day is undated.

Location evidence

Published primary facility address resolves to the matching UK postcode point via ONS-derived Postcodes.io data.1000m uncertainty covers the address area; not a surveyed building polygon.

Address
Cody Technology Park, Farnborough GU14 0LX
Country
United Kingdom
Reported operator
Datum
Location uncertainty
1000 m radius; not a surveyed boundary

Electrical work and project outlook

Probability not assessed. Builder, electrical contractor and current procurement availability are not confirmed in the published research.

Review the original sources below for the reported operator, project status and electricity infrastructure. A listed facility does not imply an open tender.

Research methodology · Entity JSON · Markdown

Location and nearby places

Nearby Bulk Supply Points and substations

No substation records within 15 km.

Nearby mine sites

No mine records within 15 km.

Sources and dates

Research compiled by Elora Grid.

  1. 01
  2. 02
  3. 03
Data notes

Distances use published location points. Nearby records may represent separate phases of one facility. Connection capacity and commissioning require current network information.