Project Camellia
Project Camellia is listed in Rincon, Georgia.
Rincon, Georgia, United States
Evidence reviewed 9 Nov 2026
Project overview
Data center project in Rincon, Georgia, with OpenAI (Octans GA LLC) listed as developer.
- Country
- United States
- State / region
- Georgia
- City or locality
- Rincon
- County
- Effingham County
- Reported developer
- OpenAI (Octans GA LLC)
- Project milestone
- 2026-09-21 · One Hundred Miles and five residents sue the Effingham IDA and Octans GA alleging open-government law violations
- Project milestone
- 2026-09-16 · Coastal Regional Commission's full DRI report released; county site plan consideration postponed at developer request
- Project milestone
- 2026-08-04 · Effingham County commissioners approve Ordinance 2026-352 permitting data centers in industrial zones
- Reported site area
- 1,400 acres
- Reported building count
- 4
- Reported floor area
- 4,400,000 sq ft
- Reported cooling design
- closed-loop
- Reported utility
- Georgia Power
- Reported water source
- Effingham County Water Treatment Plant, without line extensions
- Reported project stage
- In planning
- Status source record date
- 2026-11-08
Electrical work and project outlook
Probability not assessed. Builder, electrical contractor and current procurement availability are not confirmed in the published research.
Review the original sources below for the reported operator, project status and electricity infrastructure. A listed facility does not imply an open tender.
Nearby Bulk Supply Points and substations
No published location to calculate nearby sites.
Nearby mine sites
No published location to calculate nearby sites.
Sources and dates
Research compiled by Elora Grid.
- 01Data Center Census
Latest available status in the dated source record. Status source record date: 2026-11-08.
- 02
- 03
- 04
- 05
Data notes
Distances use published location points. Nearby records may represent separate phases of one facility. Connection capacity and commissioning require current network information.