Microsoft Silver Springs Data Center Campus
Microsoft reported site preparation, earthwork and utility relocation at Silver Springs in September 2026.
Silver Springs, Nevada, United States
Evidence reviewed 9 Nov 2026
Operator update
Microsoft reported site preparation, earthwork and utility relocation at Silver Springs in September 2026.
- Country
- United States
- State / region
- Nevada
- City or locality
- Silver Springs
- County
- Lyon
- Reported operator
- Microsoft
- Reported project stage
- Site preparation
- Status reported as of
- 2026-09
Electrical work and project outlook
Probability not assessed. Builder, electrical contractor and current procurement availability are not confirmed in the published research.
Review the original sources below for the reported operator, project status and electricity infrastructure. A listed facility does not imply an open tender.
Nearby Bulk Supply Points and substations
No published location to calculate nearby sites.
Nearby mine sites
No published location to calculate nearby sites.
Sources and dates
Research compiled by Elora Grid.
- 01Microsoft Local
Microsoft reports early site work in its September 2026 update. Status reported as of: 2026-09.