Microsoft reported site preparation, earthwork and utility relocation at Silver Springs in September 2026.

Silver Springs, Nevada, United States

View Microsoft Silver Springs Data Center Campus on the map

Site preparation

Evidence reviewed 9 Nov 2026

Operator update

Microsoft reported site preparation, earthwork and utility relocation at Silver Springs in September 2026.

Country
United States
State / region
Nevada
City or locality
Silver Springs
County
Lyon
Reported operator
Microsoft
Reported project stage
Site preparation
Status reported as of
2026-09

Electrical work and project outlook

Probability not assessed. Builder, electrical contractor and current procurement availability are not confirmed in the published research.

Review the original sources below for the reported operator, project status and electricity infrastructure. A listed facility does not imply an open tender.

Research methodology · Entity JSON · Markdown

Nearby Bulk Supply Points and substations

No published location to calculate nearby sites.

Nearby mine sites

No published location to calculate nearby sites.

Sources and dates

Research compiled by Elora Grid.

  1. 01
    Microsoft Local

    Microsoft reports early site work in its September 2026 update. Status reported as of: 2026-09.

  2. 02
  3. 03
Data notes

Distances use published location points. Nearby records may represent separate phases of one facility. Connection capacity and commissioning require current network information.