An inspection and test plan (ITP) defines the checks, acceptance criteria, hold or witness points and responsibilities for a scope of work. An inspection and test checklist (ITC), also called an inspection and test record (ITR), records the checks performed, their results, defects and sign-offs.

Updated

What is an inspection and test plan (ITP)?

An inspection and test plan (ITP) is a document that sets out, before work starts, every inspection and test a scope of work requires and how each will be verified. A typical ITP lists each activity in sequence with its acceptance criteria, the reference standard or specification clause, the verifying document, the responsible party, and the inspection type: a hold point (work stops until a check is signed off), a witness point (a party is invited to attend but work may continue), or a surveillance or review point. The ITP is a live document: it is reviewed and updated as the scope, sequence or standards change, and it acts as the roadmap for quality on the job.

What is an inspection and test checklist (ITC)?

An ITC or ITR records the checks performed under an ITP: the date, method, measured result, pass or fail status, defects, corrective action and relevant signatures. Some organisations use ITC to mean inspection and test certificate. Use the project's terminology and retain the completed record; record an authorised correction rather than silently rewriting signed evidence. A completed record can show a failure as well as a successful result.

What is the difference between an ITP and an ITC?

The difference between an ITP and an ITC is that the ITP plans the inspections and the ITC records them. The ITP comes first and is forward-looking: it defines what will be checked, against what criteria, by whom, and at which hold and witness points. The ITC comes during and after the work and is backward-looking: it is the filled-in evidence that each planned check was done and the result it gave. One ITP generates many ITCs, because the same plan is executed every time that scope is built or installed. The ITP can be revised as the job changes; a completed ITC is fixed, a quality record you keep. Put simply, you write one ITP to say how quality will be controlled, then collect many ITCs as proof that it was.

How do ITPs and ITCs show up in a tender?

A tender may require a draft ITP with the bid and completed ITCs or ITRs during manufacture, installation or handover. Capture both obligations in the package scope, including hold points, witness points, evidence and responsibility. Elora Grid can help extract these requirements from the project files and carry them into supplier enquiries. The contractor records actual test results; AI-generated text is not evidence that a test occurred.

Related resources

FAQ

Common questions

Does ITC mean inspection and test checklist or certificate?

The abbreviation varies by organisation. It commonly means inspection and test checklist, while some use certificate; inspection and test record (ITR) is another common label. Check the project quality documents and record actual results, including failures and corrective actions.

Which comes first, the ITP or the ITC?

The ITP comes first. The inspection and test plan is prepared before work starts and defines every check, its acceptance criteria and its hold and witness points. The ITC, or inspection and test record, is created during and after the work as each planned check is carried out and signed off. In other words the ITP sets the requirements and the ITCs accumulate as the evidence that those requirements were met.

Is an ITP a returnable schedule?

An ITP is often required as a returnable at bid time, but it is not itself the returnable schedule. The returnable schedules are the buyer's forms you complete and return with the bid; a project-specific ITP is frequently one of the documents those schedules or the SDRL call for. So you may submit an ITP as part of your returnables, alongside priced schedules and compliance statements, without the ITP and the returnable schedule being the same thing.

Who is responsible for the ITP and the ITCs?

The contractor or supplier doing the work usually prepares the ITP and completes the ITCs, while the client, their representative or a third-party inspector reviews and signs off at the nominated hold and witness points. Responsibilities are written into the ITP itself: one column names who carries out each check and who verifies it, so there is a clear record of accountability for every inspection and test on the job.

Put it into practice

From project files to electrical drawings.

Carry inspection, test and evidence requirements into the supplier package and deliverables list.