Elora Grid
Glossary

RFI vs clarification vs departure vs qualification

An RFI, a clarification, a departure and a qualification are four different exchanges in a tender, and they are not interchangeable. An RFI (request for information) is a question raised to close an information gap, either a buyer's pre-tender approach to the market or a bidder's formal query about the tender documents during the bid period. A clarification is an explanation of something already stated, given without changing the offer: the buyer's answer to bidders' questions, or the buyer's request that a bidder explain part of a submitted bid. A departure is a stated non-compliance against a specific clause or specification, recording exactly where your offer does not meet what was asked. A qualification is a condition you attach to your offer that changes the basis of your price, such as an exclusion, an assumption or a limit of liability. The short test: an RFI asks, a clarification explains, a departure declares non-compliance against a clause, and a qualification changes what your price actually covers.

What is an RFI in a tender, and why does the term mean two different things?

An RFI (request for information) is a question raised to close an information gap, and in tendering the term covers two different documents depending on who issues it. Issued by the buyer before a tender, an RFI is a market approach: a document sent to potential suppliers to gather capability, indicative pricing and delivery information for planning, ahead of any RFQ, RFP or RFT. US federal procurement defines that use at FAR 15.201(e), which allows an RFI when the government does not presently intend to award a contract but wants price, delivery, other market information or capabilities for planning purposes, and states that responses are not offers and cannot be accepted to form a contract. Issued by a bidder during the bid period, an RFI is a formal written question to the buyer about the tender documents: a missing drawing, a contradiction between the scope of works and the specification, an ambiguous quantity in a priced schedule. A third sense exists after award, where a contractor raises an RFI to the designer during construction. All three share the same core, which is what separates an RFI from the other three terms: an RFI asks for information that does not yet exist in the documents you hold.

What is a clarification in a tender, and how is it different from an RFI?

A clarification is an explanation of something that has already been stated, given without changing the offer, and that is exactly what separates it from an RFI: an RFI asks for information you do not have, a clarification explains information already on the table. Clarifications run in both directions. From buyer to bidders, a clarification is the buyer's written answer to bidders' questions, usually circulated to every bidder as a clarification notice or addendum so the whole field holds the same information. From buyer to one bidder after submission, it is a request that the bidder explain part of the bid, confirm a rate, or resolve an apparent error. That second direction is tightly bounded in regulated procurement, because letting a bidder improve their offer after close breaches equal treatment. US federal rules draw the line explicitly: FAR 15.306(a) treats clarifications as limited exchanges when award without discussions is contemplated, and they may not be used to cure proposal deficiencies or material omissions, materially alter the technical or cost elements of the proposal, or revise the proposal. If an exchange lets you change your offer, it is no longer a clarification.

What is a departure in a tender response?

A departure is a stated non-compliance against a specific clause or specification, declared by the bidder in their own response. It answers one question per clause: does your offer meet what was asked, and if not, exactly how does it differ. Departures are recorded clause by clause, normally in a schedule of departures or in the comply / does not comply / comply with departure column of a compliance matrix, each with a clause reference and a plain description of the difference. A departure is a technical statement about conformance, not a commercial condition. "The offered protection relay meets IEC 60255 but is not the make and model named in the specification" is a departure. Declaring departures openly is usually the safer play, because an undeclared non-compliance found during evaluation reads as either a miss or a concealment, and both damage a bid more than an honest, well-argued departure that the evaluator can weigh on its merits.

What is a qualification in a bid, and why can it get your bid set aside?

A qualification is a condition a bidder attaches to their offer that changes the basis on which the price stands: an exclusion, an assumption, a caveat on program, a limit of liability, or a condition on the contract terms. Where a departure says "this part of what you asked for is not what we are offering", a qualification says "our price only holds if the following is true". Typical examples: price excludes site establishment; assumes free issue of the switchboard by the principal; assumes uninterrupted site access between stated dates; offered on our standard terms with liability capped at contract value. Qualifications are the most dangerous of the four, because they are the ones most likely to make a bid non-conforming. Many tenders state that unqualified offers are required, or that qualified offers may be set aside, so an assumption typed into a schedule at midnight to protect the estimator can remove the whole bid from evaluation. Every qualification should be a deliberate, priced, deliberately worded decision made with the bid manager, never a stray sentence carried over in a cover letter.

Do these four terms mean the same thing in the US, UK/EU and Australia?

The four concepts exist in every region, but the labels and the rules around them differ, so bidding across regions means mapping the words before mapping the content. In Australia and the UK, departure and schedule of departures are the standard terms, qualification is used exactly as described above, bidder questions during the tender period are called RFIs or tender queries, and the buyer's replies are issued as addenda or clarification notices. In the United States, the same non-compliances are more often called exceptions or deviations and listed in an exceptions log or a clarifications and exceptions attachment, and the word clarification itself carries a specific regulatory meaning under FAR 15.306(a), a limited exchange that may not revise a proposal. In the EU, the buyer's power to seek missing or unclear material is set by Article 56(3) of Directive 2014/24/EU, which lets a contracting authority ask an economic operator to submit, supplement, clarify or complete information within an appropriate time limit, provided the request complies with equal treatment and transparency; non-compliances are often described as derogations. An American evaluator reading your schedule of departures and an Australian evaluator reading your exceptions log are looking for the same thing under a different name.

How do bid teams keep all four straight, and where does it go wrong?

Bid teams keep these four straight by running a register for each with one named owner, because the failure is almost never a definition problem, it is a tracking problem across a document set too large to re-read by hand. Four failures recur. An RFI answer arrives as an addendum late in the bid period and never reaches the estimator who priced the affected scope. A departure is agreed in a technical review but never transcribed into the compliance matrix, so the submitted pack claims full compliance the team never intended to give. A qualification survives from a previous bid's cover letter into this one, conditioning the price on something that does not apply to this job. A clarification response contradicts a figure already sitting in a priced schedule. All four are consistency failures between documents, which is the check Elora Grid is built for: it reads the tender pack and your response together, traces each question, departure and qualification back to the clause that triggered it, and flags where a statement in one document no longer agrees with another, citing every finding to its source document and page. Whether to declare a departure or carry a qualification is a commercial judgment, and that stays with your bid manager. The tool makes sure the decision your team actually made is the one that appears in the pack that goes out.

RFI vs clarification vs departure vs qualification at a glance

TermWhat it isWho raises itWhenEffect on your offer
RFIA question that closes an information gap: the buyer's pre-tender market approach, or the bidder's formal query on the documentsBuyer (pre-tender) or bidder (during the bid period)Before the tender is issued, or during the bid period before questions closeNone on its own, though the answer may change what you price
ClarificationAn explanation of something already stated, given without changing the offerBuyer, answering all bidders or querying one submitted bidDuring the bid period, or after submission during evaluationNone: if it changes the substance of your offer it is no longer a clarification
DepartureA stated non-compliance against a specific clause or specificationBidderIn the submission, recorded clause by clauseTechnical: narrows what you are offering against the specification
QualificationA condition attached to your offer that changes the basis of the priceBidderIn the submission, usually in a schedule or cover letterCommercial: the price holds only if the condition is true, and the bid may be ruled non-conforming
FAQ

Common questions

What is the difference between an RFI and a clarification in a tender?

An RFI asks for information that is not in the documents you hold, such as a missing drawing or an unresolved contradiction in the scope. A clarification explains something already stated, without changing the offer. In practice a bidder raises an RFI during the bid period, and the buyer issues clarifications in reply, or asks a bidder to clarify part of a submitted bid during evaluation.

What is the difference between a departure and a qualification?

A departure is a technical statement: your offer does not comply with a specific clause or specification, and you state exactly how it differs. A qualification is a commercial condition: your price holds only if a stated assumption or exclusion is true. Departures are recorded clause by clause in a compliance matrix; qualifications attach to the offer itself and are the more common cause of a bid being ruled non-conforming.

Can a clarification be used to fix a mistake in a submitted bid?

Usually not. In regulated procurement a clarification cannot change the substance of your offer, because that would breach equal treatment between bidders. US federal rules state this directly: under FAR 15.306(a), clarifications may not cure deficiencies or material omissions, materially alter technical or cost elements, or revise the proposal. Minor or clerical errors can sometimes be resolved, but a pricing or scope error generally cannot.

Should we declare a departure or stay silent about it?

Declare it. An undeclared non-compliance discovered during evaluation reads as either a miss or a concealment, and both damage a bid more than an honest departure with a clear technical justification. A well-worded departure gives the evaluator something to assess and, on many tenders, something to accept. Staying silent removes that option and puts the truth of your own compliance statement at risk.

Is an RFI the same as a request for proposal?

No. An RFI (request for information) gathers market information and does not lead directly to an award, while an RFP (request for proposal) asks suppliers to submit a priced, evaluable offer. FAR 15.201(e) makes the distinction explicit for US federal buyers: responses to an RFI are not offers and cannot be accepted to form a contract. An RFI often precedes an RFP or RFT.

Send a real tender. Get the output back.

Hand Elora Grid one real task and judge the result yourself.