Skip to content
Elora GridLand & Grid
Data centre · Australia · New South Wales

51 Huntingwood Drive — site certificates

The retained 51 Huntingwood Drive record contains twenty-eight post-consent certificates and names A.W. Edwards as a certificate builder. This site history remains separate from the reduced-scale modification and the operator's SYD3 campus description.

Huntingwood, New South Wales, Australia

View 51 Huntingwood Drive — site certificates on the map

Evidence reviewed 5 Nov 2026

Documented scope

The retained 51 Huntingwood Drive record contains twenty-eight post-consent certificates and names A.W. Edwards as a certificate builder. This site history remains separate from the reduced-scale modification and the operator's SYD3 campus description.

Project research: Modification 1 51 Huntingwood Drive Data Centre - Reduced Scale.

Address
51 Huntingwood Drive, Huntingwood NSW 2148
Country
Australia
State / region
New South Wales
Reported operator
AirTrunk
Source date
2026-10-21
Record scope
Site applications and certificates

Electrical work and project outlook

Probability not assessed. Builder, electrical contractor and current procurement availability are not confirmed in the published research.

Review the original sources below for the reported operator, project status and electricity infrastructure. A listed facility does not imply an open tender.

Research methodology · Entity JSON · Markdown

Location and nearby places

Nearby Bulk Supply Points and substations

75 records within 15 km.

Show 70 more
4.0 km
Sydney West Bulk Supply Point (BSP)Eastern Creek, New South Wales, AustraliaExisting infrastructure
4.9 km
6.8 km
7.5 km
10.4 km
11.9 km
12.0 km
Kemps Creek 132kV BSPNew South WalesOperational
13.1 km

Nearby mine sites

No mine records within 15 km.

Sources and dates

Research compiled by Elora Grid.

  1. 01
    Original source

    2026-10-21

  2. 02
  3. 03
  4. 04
Data notes

Distances use published location points. Nearby records may represent separate phases of one facility. Connection capacity and commissioning require current network information.