Why does the split matter at tender?
Because each side of it is priced from different things. Supply carries the equipment cost, factory testing, freight, documentation and the warranty, while the works side is mostly hours: labour, plant hire, cabling, terminations and site testing.
The trouble sits at the joins. The switchboard supplier delivers to the plinth and the electrical contractor's scope starts at the incoming cable, so who lands that cable on the board's terminals, and who tests the joint? When the pack doesn't say, each tenderer assumes the other party does it, and the work appears in nobody's price.
What belongs in a scope of supply?
The equipment itself, with ratings and quantities, plus everything that travels with it: drawings for approval, manuals, test certificates and the other documents on the supplier data requirements list. Factory acceptance testing belongs here, and so does the delivery point, which matters more than it looks. Delivered to site is not the same as delivered to the plinth, set down and unpacked.
Spares and supervision are where supply quotes vary most. One supplier includes three days of installation supervision in the price, and the next leaves it out without a word.
What belongs in a scope of works?
Everything done on site. Civil work such as plinths, cable pits and trenches, then installation, cabling, terminations, earthing, site acceptance testing and commissioning, plus the temporary works and access needed to do it.
Commissioning is the usual grey zone. The installer runs it, but the equipment supplier often has to attend for anything beyond basic checks, and nobody checks whether that attendance made it into either price.
How does the equipment list settle it?
One row per item and one column per responsibility: supplied by, delivered to, installed by, connected and tested by, commissioned by. Filled in from the scope, the specification and the drawings, the list shows every blank cell at once, and each blank is a question for the clarification period.
Draw the battery limit too. A line on the single line diagram or the GA marking where your scope ends answers in one picture what three paragraphs of scope text leave open.
An equipment list with the responsibilities split (illustrative)
| Item | Supplied by | Installed by | Connected and tested by | Commissioned by |
|---|---|---|---|---|
| 11 kV switchboard | Contractor | Contractor | Contractor | Contractor, supplier attends |
| Transformer | Client, free issue | Contractor | Contractor | Not stated |
| Plinths and cable pits | Not stated | Not stated | n/a | n/a |
| Incoming HV cable | Network operator | Network operator | Not stated | Network operator |